Oracle Primavera - PM6 Member for 17 years 8 months Member for 17 years 8 months Submitted by shiv rao on Thu, 2008-06-26 10:34 Permalink RE: Productivity factor in P5 You need to use Global Chaneg . And select Activity Resource Assignment . Change Budgeted units for All REsources from 1 to 1.15 regards shiv Member for 18 years Member for 18 years Submitted by Larry Rino on Wed, 2008-06-25 05:17 Permalink RE: Productivity factor in P5 Sorry but you need to input the new figures (+15%) manually... Good day Member for 23 years 11 months Member for 23 years 11 months Submitted by David Forrest on Mon, 2008-06-23 08:33 Permalink RE: Productivity factor in P5 You can try increasing resource max units/time to 115% and recalculate. Log in or register to post comments
Member for 17 years 8 months Member for 17 years 8 months Submitted by shiv rao on Thu, 2008-06-26 10:34 Permalink RE: Productivity factor in P5 You need to use Global Chaneg . And select Activity Resource Assignment . Change Budgeted units for All REsources from 1 to 1.15 regards shiv
Member for 18 years Member for 18 years Submitted by Larry Rino on Wed, 2008-06-25 05:17 Permalink RE: Productivity factor in P5 Sorry but you need to input the new figures (+15%) manually... Good day
Member for 23 years 11 months Member for 23 years 11 months Submitted by David Forrest on Mon, 2008-06-23 08:33 Permalink RE: Productivity factor in P5 You can try increasing resource max units/time to 115% and recalculate.
Member for
17 years 8 monthsRE: Productivity factor in P5
You need to use Global Chaneg .
And select Activity Resource Assignment .
Change Budgeted units for All REsources from 1 to 1.15
regards
shiv
Member for
18 yearsRE: Productivity factor in P5
Sorry but you need to input the new figures (+15%) manually...
Good day
Member for
23 years 11 monthsRE: Productivity factor in P5
You can try increasing resource max units/time to 115% and recalculate.