Percent complete issue

Member for

22 years 4 months

This is simple. Been there, done that.



Turn Schedule A into a baseline.

Display Schedule % Complete in your column.



Done. Good huh?

This was not possible in P3!



Cheers



Jorge Taguinod


Member for

19 years 6 months

Yep, I concur with Mr K. Load Schedule A as the baseline to B. Or, even simpler if understand the situation; Take A, make a baseline (save a copy of current programme) and thus mark progress against the client programme. No need for a B really.

If you load costs onto A and then baseline you can derive earned value...

Member for

21 years

I have not quite followed what you are trying to do... BUT what is wrong with converting the original project into a baseline?



The "Maintain Baselines" option lets you do this



??

Member for

19 years 1 month

depending on the percent complete type you had chosen, update both schedules (A & B) consistently using the same data date