Oracle Primavera - PM6 Member for 21 years Member for 21 years 1 month Submitted by David Kelly on Fri, 2008-05-02 05:31 Permalink RE: P6 & Committments The resource lag in P6 can exceed the activities duration, but you need to make sure the "Drive activity dates by default" switch is off. Have some fun and give the "income" resources a negative value, and build project cash flow curves. Log in or register to post comments
Member for 21 years Member for 21 years 1 month Submitted by David Kelly on Fri, 2008-05-02 05:31 Permalink RE: P6 & Committments The resource lag in P6 can exceed the activities duration, but you need to make sure the "Drive activity dates by default" switch is off. Have some fun and give the "income" resources a negative value, and build project cash flow curves.
Member for
21 yearsRE: P6 & Committments
The resource lag in P6 can exceed the activities duration, but you need to make sure the "Drive activity dates by default" switch is off.
Have some fun and give the "income" resources a negative value, and build project cash flow curves.