Oracle Primavera - PM6 Member for 17 years 6 months Member for 17 years 6 months Submitted by Satya Narayana on Thu, 2008-05-01 03:48 Permalink RE: Timje distribution of the Budget on WBS Thanks Mohamed it works. Member for 20 years 11 months Member for 20 years 11 months Submitted by Mohammed Abo El Magd on Thu, 2008-05-01 03:18 Permalink RE: Timje distribution of the Budget on WBS Yes sat, it could be done. Just add new activity with Activity type WBS Summery, then assign the budgeted cost on this summery activity. This also could be done on the project level by Level of effort activity. On the EPS level, you should go to the traking layout. Regards Mohamed Log in or register to post comments
Member for 17 years 6 months Member for 17 years 6 months Submitted by Satya Narayana on Thu, 2008-05-01 03:48 Permalink RE: Timje distribution of the Budget on WBS Thanks Mohamed it works.
Member for 20 years 11 months Member for 20 years 11 months Submitted by Mohammed Abo El Magd on Thu, 2008-05-01 03:18 Permalink RE: Timje distribution of the Budget on WBS Yes sat, it could be done. Just add new activity with Activity type WBS Summery, then assign the budgeted cost on this summery activity. This also could be done on the project level by Level of effort activity. On the EPS level, you should go to the traking layout. Regards Mohamed
Member for
17 years 6 monthsRE: Timje distribution of the Budget on WBS
Thanks
Mohamed it works.
Member for
20 years 11 monthsRE: Timje distribution of the Budget on WBS
Yes sat, it could be done. Just add new activity with Activity type WBS Summery, then assign the budgeted cost on this summery activity.
This also could be done on the project level by Level of effort activity.
On the EPS level, you should go to the traking layout.
Regards
Mohamed