Timje distribution of the Budget on WBS

Member for

20 years 11 months

Yes sat, it could be done. Just add new activity with Activity type WBS Summery, then assign the budgeted cost on this summery activity.



This also could be done on the project level by Level of effort activity.



On the EPS level, you should go to the traking layout.



Regards

Mohamed