Schedule % and Performance % Summery

Member for

18 years 8 months

Mohammed,

At least you fixed it.



I’ll track the guy down at work next week if I remember and ask him what our problem was again, I thought it was the same but that didn’t sound like the same fix.



Andy

Member for

20 years 11 months

Wallla,

I found it, I got the solution,

I must assign resources with unit price even 1$, that is when the summery for S PCT% & P PCT% will be calculated.



Regards

Mohamed

Member for

20 years 11 months

Dear Andrew,

I do not know, but it dose not work. Stil facing the same problem. I’ve repeated the whole project,yet with no use.



Thank you for interacting.

Mohamed

Member for

18 years 8 months

Mohammed,

Came across this one the other week, and a bloke I know came up with the soloution.



In a nutshell the fault existed for us when we deleted an activity out of the project which existed in the baseline.



So you will need to carry out a new baseline and the missing data will be returned.



I’m sure that’s how it went, I’ll check tomorrow.



Andy