You will need to use 2 action statements, one to do the Actual/At Completion part and then another to multiply this result by 100 to arrive at a percentage value.
Member for
20 years 7 months
Member for20 years7 months
Submitted by Yasser Elyosefi on Mon, 2008-03-03 07:39
Member for
20 years 7 monthsRE: Level of effort activity’s actual progress
That means there is no built-in function in P6 to do it ??!!
Member for
23 yearsRE: Level of effort activity’s actual progress
Use a Global Change
You will need to use 2 action statements, one to do the Actual/At Completion part and then another to multiply this result by 100 to arrive at a percentage value.
Member for
20 years 7 monthsRE: Level of effort activity’s actual progress
Thanks. But in this case I need to manually calculate the progress every time I update the schedule
My target is to set the level of effort activity to automatically calculate progress as follows:
Activity % Complete = Actual duration / At Completion duration.
Is there a way for that? How?
Member for
23 yearsRE: Level of effort activity’s actual progress
Change the Percent Complete Type to Physical