I’m not sure I conveyed what it is I am trying to do well enough. I need to actually change each Budgeted Nonlabour Cost field to match the At Completion Nonlabour Cost against each indivual activity.
Rather than doing this manually one by one is there a fast way to make one match the other on every activty?
Thanks,
Nathan
Member for
18 years 9 months
Member for18 years10 months
Submitted by Dieter Wambach on Tue, 2008-01-15 09:58
Youll need a Baseline. Then you can display: "Variance - BL Project Nonlabor Cost". (right mouse click in the table area --> Columns --> costs --> BL... )
Member for
18 years 9 monthsRE: Quick cost update
Hi Nathan
First, Im not 100% sure for my reply:
1. Budgeted Costs for an assignment is by default calculated rate*units.
2. You may set a different rate, if for "rate source" override is selected.
3. You may set a parameter for a project - under the tab "calculations" - that units will be calculated on costs.
Then you may create a global change in the goup "resource assigments".
"If budgeted non-labour units > 0 (or any appropriate criterium)
Then Budgeted Cost = At Completion cost"
The walkthrough will be by assignment and so budgeted cost will be for this specific assignment.
Hope this will help
Dieter
Member for
17 years 11 monthsRE: Quick cost update
Thanks Dieter,
I’m not sure I conveyed what it is I am trying to do well enough. I need to actually change each Budgeted Nonlabour Cost field to match the At Completion Nonlabour Cost against each indivual activity.
Rather than doing this manually one by one is there a fast way to make one match the other on every activty?
Thanks,
Nathan
Member for
18 years 9 monthsRE: Quick cost update
Hi Nathan
Youll need a Baseline. Then you can display: "Variance - BL Project Nonlabor Cost". (right mouse click in the table area --> Columns --> costs --> BL... )
Regards
Dieter