Progress percentage and scope of work

Member for

10 years 1 month

Dear Sunil.

       I thing is better to remove the remaining tasks regarding the building and get the new baseline and do analysing what you have to complete.

 

 

Cheer

SAADI 

Member for

15 years

Thanks Gary

Member for

16 years 7 months

It depends on what your contract says.

 

Some contract forms have no mechanism for a change in scope to bring the contractual completion date forward, some do.

Some contracts require a project to be re-baselined with every major contract variation,some don't.

Read your contract and/or check with your contract manager

 

If this is not a contractual issue, and you are talking about an internal baseline purely used to mintor project progress rather than manage the contract, then re-baselining will give you a more accurate measure of project progress.