Delay by total float vs. delay by variance

Member for

16 years 3 months

one this assumes that the correct baseline has been assigned ot the current schedule

the variance dates (BL FInish - Finish) is comparing the finsh dates of the two schedules and will show positive abd well as negative variances between the 2 dates. It is the difference between the activity's baseline and current finish date.

the variance dates (BL FInish - Finish) will give you values even if the activity has been completed

when only looking at float values there wil not be any float values once and activity has been completed.

be careful because there is a difference between the BL Finish the , Finish and the Late Finish Dates

The BL Finish is the Early Finish date in the baselie schedule

The Fnish date is the Early Finish date in the current schedule unless its an actual date

The late finish dates minus the early finish n the current schedule will be used to determine the float values