Resource Assignment summary

Member for

16 years 3 months

open Project / Resource Assignments 

upper left under layout there is a small upside down triangle click on it 

select filter and make sure that you have the correct filter set

also same place for columns select default 

 

 

 

Member for

15 years

Zoltan,

Resource usage profile is working fine, problem is that when we open Project / Resource Assignments ..it is not displaying anything. Any Report settings we have to change or not.

Best Regards,

Sunil.

Member for

16 years 3 months

if you have assigned a resource to all of your activiites you can select view show on bottom and select resource usage profile

then on the right hand side click resource usage profile options

in the data tab make sure that units is checked  

in the graph tab make sure that calculate average is checked and that Base on hours per time period is checked 

right click the graph area and select timescale and select Year/Month as the time interval 

Member for

15 years

Hi Vladimir,

The software is P6 Ver 7.1

Best Regards,

Sunil.

Member for

24 years 9 months

Hi Sunil,

I can answer  to your question explaining where to find all the data on resource assignments in Spider Project. It looks like you mean some other software. Is it present in the discussion forums here? PP has forums on P6, P3, MS Project, Asta, Sciforma, etc. Please specify the software that you use if it is absent in the PP list or put your question in the discussion forum on your software.