What are the ways to adjust the out of sequence activities in a project, please choose the kind of activity like a physical,duration and units. Convert the activity into the phyiscal percent complete.
When scheduling use the progress override options in scheduling tab....
Member for
10 years 5 months
Member for10 years6 months
Submitted by cearslanshahid on Thu, 2015-06-11 12:11
You usually change the logic to account for out of sequence progress.
You never ever change the baseline this was your original plan an your concept of how the project was going to be performed.
As you update the schedule things change for whatever reason and you are forced to do things differently hence the out of sequence progress.
Why in the world would you want to go back and change or baseline logic based on things that you had no idea were going to happen.
The WHOLE purpose of a baseline is so that it can be used to compare the original plan to the current plan and note the differences.
What you want to do is like originally planning a trip from New York to Los Angeles to drive it in 4 days = Baseline
Now something happens along the way and you have to stop in Miami first then from Miami you can proceed to Los Angeles this now adds 1 more day of travel time to your trip make it 5 days instead of 4 days = Update and out of sequence because you added the stop in Miami.
So with the basline line logic and sequence intact you can see that it originally was going to take 4 days for your trip but due to the added stop in Miami it is now going to take 5 days to complete your trip.
If you go back and change the original plan to include the added stop in Miami how could you ever compare the original plan vs the current plan ? You could not do it.
The baseline is your measuring stick NEVER change it.
Member for
24 years 5 months
Member for24 years5 months
Submitted by Andrew Pearce on Sun, 2015-06-07 10:59
In my humble opinion you have to make changes to relationships in the current version of the schedule. This is to reflect the actual sequence in which works were executed. You do not cahnge anything in the baseline.
The baseline being what you originally planned to do and the current version being what you actually did.
Member for
10 years 5 monthsWhat are the ways to adjust
What are the ways to adjust the out of sequence activities in a project, please choose the kind of activity like a physical,duration and units. Convert the activity into the phyiscal percent complete.
When scheduling use the progress override options in scheduling tab....
Member for
10 years 5 monthsDear zoltan palffy, Thank you
Dear zoltan palffy,
Thank you very much. You explained it brilliantly.
Regards,
Member for
16 years 3 monthsI agree with AndrewYou
I agree with Andrew
You usually change the logic to account for out of sequence progress.
You never ever change the baseline this was your original plan an your concept of how the project was going to be performed.
As you update the schedule things change for whatever reason and you are forced to do things differently hence the out of sequence progress.
Why in the world would you want to go back and change or baseline logic based on things that you had no idea were going to happen.
The WHOLE purpose of a baseline is so that it can be used to compare the original plan to the current plan and note the differences.
What you want to do is like originally planning a trip from New York to Los Angeles to drive it in 4 days = Baseline
Now something happens along the way and you have to stop in Miami first then from Miami you can proceed to Los Angeles this now adds 1 more day of travel time to your trip make it 5 days instead of 4 days = Update and out of sequence because you added the stop in Miami.
So with the basline line logic and sequence intact you can see that it originally was going to take 4 days for your trip but due to the added stop in Miami it is now going to take 5 days to complete your trip.
If you go back and change the original plan to include the added stop in Miami how could you ever compare the original plan vs the current plan ? You could not do it.
The baseline is your measuring stick NEVER change it.
Member for
24 years 5 monthsIn my humble opinion you have
In my humble opinion you have to make changes to relationships in the current version of the schedule. This is to reflect the actual sequence in which works were executed. You do not cahnge anything in the baseline.
The baseline being what you originally planned to do and the current version being what you actually did.