Planning, Scheduling & Programming Discussion Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Wed, 2014-04-09 18:31 Permalink Hi HaythamSet up a Hi Haytham Set up a spreadsheet with the dimensions of each concrete component - floors - columns - beams - stairs ect. This will give you the total m3 of concrete in the project. Put a date column in the spreadsheet. Every day collect a copy of the concrete cube test sheets and type the date of the test against the concrete item. You can then keep a running total of actual concrete production to compare with your planned production rate. Best regards Mike Testro Log in or register to post comments
Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Wed, 2014-04-09 18:31 Permalink Hi HaythamSet up a Hi Haytham Set up a spreadsheet with the dimensions of each concrete component - floors - columns - beams - stairs ect. This will give you the total m3 of concrete in the project. Put a date column in the spreadsheet. Every day collect a copy of the concrete cube test sheets and type the date of the test against the concrete item. You can then keep a running total of actual concrete production to compare with your planned production rate. Best regards Mike Testro
Member for
19 years 10 monthsHi HaythamSet up a
Hi Haytham
Set up a spreadsheet with the dimensions of each concrete component - floors - columns - beams - stairs ect.
This will give you the total m3 of concrete in the project.
Put a date column in the spreadsheet.
Every day collect a copy of the concrete cube test sheets and type the date of the test against the concrete item.
You can then keep a running total of actual concrete production to compare with your planned production rate.
Best regards
Mike Testro