Activity % Complete in Totals and Sub-totals do not appear

Member for

15 years 11 months

Hey Arvin , i got your problem. Understand one thing P6 never shows summary % complete in Activity % column. Chew on it. To know % progress at summary level you have to add Performance % Complete column.

Now switch to P6 and do that first before you continue.

 

Voila!! there you go, now you can see the % complete and can thank me for that.

 

However if P6 still doesnt show the % complete at sumary level follow the below steps.

I want you to check if you have assigned cost for your resources.

If not, P6 is not going to give you a damn % complete on Summary level.

So you have two options:-

1. If you do not want your schedule to be cost loaded, just put resource Price/unit as 1/unit. Recalculate assignment cost. This will get you going. Or

2. Load the actual cost of resources and materials, you have the % complete in summary bars.

I hope this solves your problem.

Regards,

Ranga

Member for

16 years 7 months

Arvin,

 

It works for me, so not sure what to advise. -Have you baselined?

Member for

17 years 5 months

Hi Arvin,

Activity percent complete will not roll up (summary%) to WBS level, only for each activities.

 

kannan

Member for

11 years 7 months

Hi Gary,

I do the steps you advised. Still it did not show.

Thanks.

Arvin

Member for

11 years 7 months

Hi Gary,

thanks.

Arvin

Member for

16 years 7 months

1) Admin > Admin preferences > Earned Value. Ensure "techique for calculating performance % complete" is selected as "activty % complete"

2) Display the column "performance % complete". This will show in totals.

 

Cheers,



G