Hey Arvin , i got your problem. Understand one thing P6 never shows summary % complete in Activity % column. Chew on it. To know % progress at summary level you have to add Performance % Complete column.
Now switch to P6 and do that first before you continue.
Voila!! there you go, now you can see the % complete and can thank me for that.
However if P6 still doesnt show the % complete at sumary level follow the below steps.
I want you to check if you have assigned cost for your resources.
If not, P6 is not going to give you a damn % complete on Summary level.
So you have two options:-
1. If you do not want your schedule to be cost loaded, just put resource Price/unit as 1/unit. Recalculate assignment cost. This will get you going. Or
2. Load the actual cost of resources and materials, you have the % complete in summary bars.
I hope this solves your problem.
Regards,
Ranga
Member for
16 years 7 months
Member for16 years7 months
Submitted by Gary Whitehead on Thu, 2014-03-27 08:58
Member for
15 years 11 monthsHey Arvin , i got your
Hey Arvin , i got your problem. Understand one thing P6 never shows summary % complete in Activity % column. Chew on it. To know % progress at summary level you have to add Performance % Complete column.
Now switch to P6 and do that first before you continue.
Voila!! there you go, now you can see the % complete and can thank me for that.
However if P6 still doesnt show the % complete at sumary level follow the below steps.
I want you to check if you have assigned cost for your resources.
If not, P6 is not going to give you a damn % complete on Summary level.
So you have two options:-
1. If you do not want your schedule to be cost loaded, just put resource Price/unit as 1/unit. Recalculate assignment cost. This will get you going. Or
2. Load the actual cost of resources and materials, you have the % complete in summary bars.
I hope this solves your problem.
Regards,
Ranga
Member for
16 years 7 monthsArvin, It works for me, so
Arvin,
It works for me, so not sure what to advise. -Have you baselined?
Member for
17 years 5 monthsHi Arvin,Activity percent
Hi Arvin,
Activity percent complete will not roll up (summary%) to WBS level, only for each activities.
kannan
Member for
11 years 7 monthsHi Gary,I do the steps you
Hi Gary,
I do the steps you advised. Still it did not show.
Thanks.
Arvin
Member for
11 years 7 monthsHi Gary,thanks.Arvin
Hi Gary,
thanks.
Arvin
Member for
16 years 7 months1) Admin > Admin preferences
1) Admin > Admin preferences > Earned Value. Ensure "techique for calculating performance % complete" is selected as "activty % complete"
2) Display the column "performance % complete". This will show in totals.
Cheers,
G