Milestones and Key dates WBS

Member for

14 years 3 months

Thanks again Raymund, a friend here also suggested the same solution. However, I think I finally got around to group by Activity code as well as WBS. I appreciate your inputs man!

Cheers,

Abdulhafiz

Member for

15 years 11 months

Create another Activity codes with the same name as your WBS.

Member for

14 years 3 months

Thanks Raymund, I follow your reasoning but the challenge Im having with Activity codes is that is will just group the schedule into "Milestones" and "No Milestones" categories which is not so cool for presentation purposes. Or is there a way to group by Activity codes as well as WBS especially in P6? Thanks again for inputs.

 

Regards,

Abdulhafiz

Member for

15 years 11 months

AbdulHafiz,

I suggest you insert those key dates within the same WBS with the related tasks and create acitivty codes to group milestone/key dates altogether for reporting purposes organized by activty codes accordingly.