I am not much more experienced but i feel i can help you on this, no problem cost or resource not needed but are u using the planning tool of Primavera 6 or MS project. the % Completion u selected is rite but you have to update the schedule. check the progress update and select the regarding month to be update, so u will get it.
Member for
13 years 9 monthsI suggest you dont use
I suggest you dont use Perfomance % if your schedule is not cost loaded.
Member for
13 years 10 monthsHi Bim, I am not much
Hi Bim,
I am not much more experienced but i feel i can help you on this, no problem cost or resource not needed but are u using the planning tool of Primavera 6 or MS project. the % Completion u selected is rite but you have to update the schedule. check the progress update and select the regarding month to be update, so u will get it.
where are you working Bim.
Yur, & best wishes.
J. Vijay