Progress on WBS and Project Level

Member for

13 years 9 months

I suggest you dont use Perfomance % if your schedule is not cost loaded.

Member for

13 years 10 months

Hi Bim,

        I am not much more experienced but i feel i can help you on this, no problem cost or resource not needed but are u using the planning tool of Primavera 6 or MS project. the % Completion u selected is rite but you have to update the schedule. check the progress update and select the regarding month to be update, so u will get it.

where are you working Bim.

Yur, & best wishes.

J. Vijay