Since the management tasked you to develope the programme in P6, try to create a P6 baseline by your own, reviewing any invalid relationships, resources, activities, durations. When you satisfy yourself that is a baseline that represents your project original scope and contractual requirements, present it your management, for refinements; incorpore comments.
After you have your P6 baseline, then you can proceed with the variation orders, maybe thru a consolidated approach, or by individual VOs.
I would just use the MS project programme done by the previous planner for reference. It would not be prudent, I think, to just export/import the previous file. Know the project documents, and do some research.
To the best of my knowledge and experties , I suggest following ,
1.Import the first and last MS Proejct files into P6 separately.
2.Assign original schedule to last schedule as a baseline.
3. Add following columns ,
3.1 Variance BL-Proejct Duration
3.2 Variance BL Project Start Date
3.3 Variance-BL Project finish Date
I believe you will have better idea how to proceed ahead.
You can send the first and last schedules to me at Imran.asghar12@gmail.com to advise you better. I will practice suggested actions and let you know how they work.
Member for
13 years 11 monthsDear Anning Sofi,I will
Dear Anning Sofi,
I will definitely give it at try on what you told and will let you know.
Thanks anyways.
KK
Member for
13 years 9 monthsSince the management tasked
Since the management tasked you to develope the programme in P6, try to create a P6 baseline by your own, reviewing any invalid relationships, resources, activities, durations. When you satisfy yourself that is a baseline that represents your project original scope and contractual requirements, present it your management, for refinements; incorpore comments.
After you have your P6 baseline, then you can proceed with the variation orders, maybe thru a consolidated approach, or by individual VOs.
I would just use the MS project programme done by the previous planner for reference. It would not be prudent, I think, to just export/import the previous file. Know the project documents, and do some research.
Member for
13 years 11 monthsThanks Imran sb.
Thanks Imran sb.
Member for
13 years 10 monthsDear Kashif, To the best of
Dear Kashif,
To the best of my knowledge and experties , I suggest following ,
1.Import the first and last MS Proejct files into P6 separately.
2.Assign original schedule to last schedule as a baseline.
3. Add following columns ,
3.1 Variance BL-Proejct Duration
3.2 Variance BL Project Start Date
3.3 Variance-BL Project finish Date
I believe you will have better idea how to proceed ahead.
You can send the first and last schedules to me at Imran.asghar12@gmail.com to advise you better. I will practice suggested actions and let you know how they work.
Regards,
Imran Asghar