Restoring XER file

Member for

13 years 11 months

Ronald,

Even when you assign a baseline and export it to .XER file, when you import and then open , you could see that baseline column shows the dates of early start and early finish and not the actual baseline dates, which implies that the baseline is not getting exported into the .XER file.

So when you make a schedule update and preserve it in .XER file, the baseline doesn't follow that file.So you have to save the original baseline and re assign it to the schedule update each time you update the schedule.

Please let me know if there is a better option

 

Best Regards,

San

Member for

13 years 11 months

You are right SM, baseline doesn't get exported.

Thanks

BR,

San

Member for

22 years 10 months

San,

You always have baseline dates, even when no baseline is assigned.  When no baseline is assigned, your current Planned Dates are displayed as the baseline dates.  This is probably why you think that they have ‘changed.’  The baseline dates did not change, the baseline probably did not transfer or it is no longer assigned.  Good luck!

Member for

13 years 11 months

san TS

When you export .XER file then Baseline is not exported.You hace to Restore it.

 

Regards