Planning, Scheduling & Programming Discussion Member for 13 years 10 months Member for 13 years 10 months Submitted by forrest on Wed, 2012-01-18 06:14 Permalink Hi,If it is the first Hi, If it is the first activity (normally a start milestone), then you need to give it a contraint as 'start on'; as for other activities, you can either constrain them (not recommended) or logically link them together. Hope the above helps with you question. Log in or register to post comments
Member for 13 years 10 months Member for 13 years 10 months Submitted by forrest on Wed, 2012-01-18 06:14 Permalink Hi,If it is the first Hi, If it is the first activity (normally a start milestone), then you need to give it a contraint as 'start on'; as for other activities, you can either constrain them (not recommended) or logically link them together. Hope the above helps with you question.
Member for
13 years 10 monthsHi,If it is the first
Hi,
If it is the first activity (normally a start milestone), then you need to give it a contraint as 'start on';
as for other activities, you can either constrain them (not recommended) or logically link them together.
Hope the above helps with you question.