In Spider Project this field is called Activity Volume. Volume is a standard field and entering activity Volume and assigned resource productivities you don't need to enter activity duration - it is calculated by the software.
You may define material requirements per unit of volume, unit costs, resource assignment costs depending on volumes performed, etc.
In other softwares you shall use UDF as Mike proposed.
Member for
24 years 9 monthsIn Spider Project this field
In Spider Project this field is called Activity Volume. Volume is a standard field and entering activity Volume and assigned resource productivities you don't need to enter activity duration - it is calculated by the software.
You may define material requirements per unit of volume, unit costs, resource assignment costs depending on volumes performed, etc.
In other softwares you shall use UDF as Mike proposed.
Member for
14 years 6 monthsHi Vineet, What mike has
Hi Vineet,
What mike has written above holds true. Further if you can send me snapshot of the schedul of questioned area i shall be able to answer it
Member for
14 yearshi mike, sorry to ask u
hi mike,
sorry to ask u again..if u dont mind please explain..
Member for
19 years 10 monthsHi Vineeth You can set up
Hi Vineeth
You can set up user defined columns for this data or place the information on your resource modelling section.
Best regards
Mike Testro