Critical Path Question

Member for

17 years

Faiz

As mike said it is not good practise to cheat the software.:: Dont make non critical activity to the crivitical activity by applying constraints, 

Software do as we say,. it gives critical as per the instruction gives by us, so our instructions to the software should be clear,...Proper links, relationships, resource flow, resource links, understanding critical path concept required,,,,,

If you dont do your resource critical Path your scheduling would be fail,,, please be aware of this,

 

Member for

17 years 5 months

Faiz,

 

Why you want non-critical activities in the critical path. I think no benefit from it. If your Programme reflects the real situation of the site activities, then the Software Critical Path will match to your requirements.

 

Member for

19 years 10 months

Hi Geoff

Using constraints to force a critical path is bad planning practice.

As Gary says - don't try to cheat the software.

Best regards

Mike Testro

Member for

15 years

what  you need to do if you don't want to see float is to create them by placing finish on or before constraint. that shoul generate some float....... or check to find errors....

Member for

16 years 7 months

the only legitimate technique is to review the schedule and correct any mistakes.

 

Forcing an activity to be critical when it isn't is pure deception, and not something I would condone.