Next most obvious thing to check is if there is a constraint at the project level.
Assuming you are using P6 (most do), you can check this from Enterprise > Projects. Right-click on your project from the EPS structure and select "Project Details". Go to the "Dates" tab and check that the "Must Finish By" field is blank
If it's not this, calendars would be the next thing I'd look at.
Member for
16 years 7 monthsNext most obvious thing to
Next most obvious thing to check is if there is a constraint at the project level.
Assuming you are using P6 (most do), you can check this from Enterprise > Projects. Right-click on your project from the EPS structure and select "Project Details". Go to the "Dates" tab and check that the "Must Finish By" field is blank
If it's not this, calendars would be the next thing I'd look at.
Member for
14 years 4 monthsThanks Mike for The
Thanks Mike for The Reply.There is no constraint in my Schedule.I have checked all activities.
Member for
19 years 10 monthsHi Faiz There could be any
Hi Faiz
There could be any number of reasons but the most common is that you have some Must End By constraints.
Remove ALL constraints and reschedule.
Best regards
MikeTestro