Critical Path Change

Member for

16 years 7 months

Next most obvious thing to check is if there is a constraint at the project level.

Assuming you are using P6 (most do), you can check this from Enterprise > Projects. Right-click on your project from the EPS structure and select "Project Details". Go to the "Dates" tab and check that the "Must Finish By" field is blank

 

If it's not this, calendars would be the next thing I'd look at.

Member for

14 years 4 months

Thanks Mike for The Reply.There is no constraint in my Schedule.I have checked all activities.

Member for

19 years 10 months

Hi Faiz

There could be any number of reasons but the most common is that you have some Must End By constraints.

Remove ALL constraints and reschedule.

Best regards

MikeTestro