Comparison Between Baseline Program & Revised target program

Member for

13 years 10 months

If interpreted correctly, the baseline dont change. If there is a new baseline and the sequence is the same but delayed then in this case, where activities were delayed by 4 months, everything else from the revised data date should change uniformly. in the case where items were deleted, this is not the right thing to do as you may have critical or follow on activities. But first you should do a physical comparason and identify actvities which were removed but is necessary for you to acheive your target.

Hope this helps you in the right direction

 

Amar

Member for

14 years 2 months

Hi,

Regardless of new target program, you can always compare poject activities and Milestones dates by calling the baseline coluimn and all costs, PV, EV, ETC, etc by refering to the baseline taken before.

rgrds