I am currently on a mining project and have to do plannning for shutdown and tie in with existing plant. I would appreciate if some one can send me a planning schedule which has been done in any other project. I am not very sure if Primavera is good enough to do the shutdown planning as lot of detailing and work duration in hrs needs to be used.
Thanks
Abhinav
Member for
22 years 11 months
Member for23 years
Submitted by Bernard Ertl on Thu, 2004-12-02 09:35
We recommend planning to a high degree of detail, but we use software that can handle it easily. If you are using software that bogs down with a large volume of detailed tasks, you should plan to as detailed a degree as the software can reasonably accommodate (or find another tool if the current one is inadequate).
Usually, the capital work that is integrated into a (maintenance) turnaround is limited to piping tie-ins. We code them appropriately to identify the work as capital work but otherwise treat it the same as any other part of the project scope.
The organization of the work into a WBS would be dependent upon the procedures at your plant. Every turnaround I have ever participated in used a work order based system for organizing work at (more or less) the equipment level. Something like:
Plant
- Unit
--- Equipment Type
------ Work Order
--------- Tasks
We include all pre-turnaround work in the schedule and flag it as pre-turnaround. Our system has some built-in facilities for handling pre and post turnaround work appropriately for cost estimating, scheduling, etc.
I cannot recall ever seeing design included in a turnaround plan/schedule. If you are referring to the capital projects, usually the engineer(s) overseeing the project(s) will be in charge of managing their responsibilities leading up to the construction.
Purchasing of material is usually done well before the turnaround schedule is approved/finalized and it is more common to include material delivery constraints than material purchasing activities.
I can forward you a sample schedule when I return to the office on Monday. Im guessing you are new to planning shutdowns / turnarounds? Does the plant you are at not have any data from past jobs?
Member for
19 years 10 monthsHi Abnav This is an old
Hi Abnav
This is an old thread from 2004.
Start a new thread for your new enquiry.
I have locked this one.
Member for
13 years 10 monthsHi Rusydi, Do you have any
Hi Rusydi,
Do you have any planning shcedule for shutdown works?Kindly send me as I need to prepare a shutdown program.
Abhinav
Member for
13 years 10 monthsHi Guys, I am currently on a
Hi Guys,
I am currently on a mining project and have to do plannning for shutdown and tie in with existing plant. I would appreciate if some one can send me a planning schedule which has been done in any other project. I am not very sure if Primavera is good enough to do the shutdown planning as lot of detailing and work duration in hrs needs to be used.
Thanks
Abhinav
Member for
22 years 11 monthsRE: Shutdown Schedule
We published a primer (tutorial) for planning turnarounds that you might find helpful.
We recommend planning to a high degree of detail, but we use software that can handle it easily. If you are using software that bogs down with a large volume of detailed tasks, you should plan to as detailed a degree as the software can reasonably accommodate (or find another tool if the current one is inadequate).
Usually, the capital work that is integrated into a (maintenance) turnaround is limited to piping tie-ins. We code them appropriately to identify the work as capital work but otherwise treat it the same as any other part of the project scope.
The organization of the work into a WBS would be dependent upon the procedures at your plant. Every turnaround I have ever participated in used a work order based system for organizing work at (more or less) the equipment level. Something like:
Plant
- Unit
--- Equipment Type
------ Work Order
--------- Tasks
We include all pre-turnaround work in the schedule and flag it as pre-turnaround. Our system has some built-in facilities for handling pre and post turnaround work appropriately for cost estimating, scheduling, etc.
I cannot recall ever seeing design included in a turnaround plan/schedule. If you are referring to the capital projects, usually the engineer(s) overseeing the project(s) will be in charge of managing their responsibilities leading up to the construction.
Purchasing of material is usually done well before the turnaround schedule is approved/finalized and it is more common to include material delivery constraints than material purchasing activities.
Bernard Ertl
InterPlan Systems - ATC Professional Shutdown / Turnaround Management System
Member for
21 years 9 monthsRE: Shutdown Schedule
Bernard,
Right, this my first experience in preparing Shutdown Schedule. My experience mostly in Project.
How detail s/d schedule is, so it is manageable?
How do you combine between capital work and maintenance work?
What is the basis in structuring the WBS?
How do you manage the pre-shutdown work including design and purchasing material?
Thanks for your advise.
Regards,
rusydi
Member for
22 years 11 monthsRE: Shutdown Schedule
I can forward you a sample schedule when I return to the office on Monday. Im guessing you are new to planning shutdowns / turnarounds? Does the plant you are at not have any data from past jobs?
Bernard Ertl
InterPlan Systems - ATC Professional Shutdown / Turnaround Management System
Member for
21 years 9 monthsRE: Shutdown Schedule
Actually, Im looking for sample of shutdown schedule, especially in Refinery Plant. And also Work Order, Job Card sample format.
thanks,
Member for
22 years 7 monthsRE: Shutdown Schedule
Ive a little exposure in shutdown schedule preparation, brief your query on specific item ....... let me try to solve it if i can.......
Member for
22 years 11 monthsRE: Shutdown Schedule
I have extensive experience with shutdowns/turnarounds. If you have a specific question, I would be happy to relate my perspective.
Bernard Ertl