Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Thu, 2023-06-01 14:36 Permalink you cant import start and you cant import start and finish dates those are claulated you can import constraint dates you can import actual dates 1st export 1 activity of what you want thne use that as a template to import it back into p6 Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Thu, 2023-06-01 14:36 Permalink you cant import start and you cant import start and finish dates those are claulated you can import constraint dates you can import actual dates 1st export 1 activity of what you want thne use that as a template to import it back into p6 Log in or register to post comments
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Thu, 2023-06-01 14:36 Permalink you cant import start and you cant import start and finish dates those are claulated you can import constraint dates you can import actual dates 1st export 1 activity of what you want thne use that as a template to import it back into p6
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Thu, 2023-06-01 14:36 Permalink you cant import start and you cant import start and finish dates those are claulated you can import constraint dates you can import actual dates 1st export 1 activity of what you want thne use that as a template to import it back into p6
Member for
16 years 3 monthsyou cant import start and
you cant import start and finish dates those are claulated
you can import constraint dates
you can import actual dates
1st export 1 activity of what you want thne use that as a template to import it back into p6
Member for
16 years 3 monthsyou cant import start and
you cant import start and finish dates those are claulated
you can import constraint dates
you can import actual dates
1st export 1 activity of what you want thne use that as a template to import it back into p6