Max units per time not matching "Limit" line in recourse usage profile bar chart

Member for

3 years 3 months

It Worked!!! 

You were correct. 

I deleted both calenders and added again. 

Thanks alot.

Member for

3 years 3 months

I checked that again. Calender for both activities and resources are same.

see below snapshot.

[[wysiwyg_imageupload:8277:]]

Member for

9 years 9 months

So, you think the llimit should be 50, but it is really 63?

 

Sounds like a Resource Calendar issue

Member for

3 years 3 months

It's showing 63.

Member for

3 years 3 months

It's showing 63.

Member for

9 years 9 months

Can you double-click on one of the histogram bars, and report back the figures?