Thanks all for recommendation but this activity is not an overhead. Its is task dependent and can be on CP with resource assigned to it.. The tricky part is, it dpendent on the 2 activities above it. So, in simple terms i need to relate it with the earliest start & latest finish of either of the above 2 activities.
LoE activities are terrific for 'overhead' costs and resources, and even better for collecting timesheet data that has not got any activity ID information. You cannot level the resources.
Member for
19 years
Member for19 years
Submitted by Rodel Marasigan on Mon, 2022-11-21 13:54
Of course you can use LOE for resource loading. It is a logical way of resource loading such as prelims, engineering, constuction supports, equipment usage and or summary level of resouces.
Member for
3 years 3 monthsThanks all for recommendation
Thanks all for recommendation but this activity is not an overhead. Its is task dependent and can be on CP with resource assigned to it.. The tricky part is, it dpendent on the 2 activities above it. So, in simple terms i need to relate it with the earliest start & latest finish of either of the above 2 activities.
Member for
9 years 9 monthsLoE activities are terrific
LoE activities are terrific for 'overhead' costs and resources, and even better for collecting timesheet data that has not got any activity ID information. You cannot level the resources.
Member for
19 yearsOf course you can use LOE for
Of course you can use LOE for resource loading. It is a logical way of resource loading such as prelims, engineering, constuction supports, equipment usage and or summary level of resouces.
Member for
3 years 3 monthsThanks, But i need to assign
Thanks, But i need to assign resoureces to it. Not sure if that will work with LOE and might need to reosurce level it too in future.
Member for
3 years 3 monthsThanks, But i need to assign
Thanks, But i need to assign resoureces to it. Not sure if that will work with LOE and might need to reosurce level it too in future.
Member for
3 years 3 monthsThanks, But i need to assign
Thanks, But i need to assign resoureces to it. Not sure if that will work with LOE and might need to reosurce level it too in future.
Member for
21 years 8 monthshttps://boyleprojectconsultin
https://boyleprojectconsulting.com/tomsblog/2017/11/06/constructing-lev…
Member for
19 yearsThe only way is to use LOE as
The only way is to use LOE as per below:
A1170 - LOE Activity
Predecessor A1130 SS
Successor A1160 FF