because constraints not allowed, contractor put in new calendars that do the same thing...

Member for

3 years 10 months

How would you show potential risk incurred by poor weather condition in the schedule?

Would you prefering a single contingency activity at the end of the schedule stating it's used to account for all potential risks?

Member for

3 years 10 months

How would you show potential risk incurred by poor weather condition in the schedule?

Would you prefering a single contingency activity at the end of the schedule stating it's used to account for all potential risks?

Member for

9 years 9 months

Contractors do what the contract allows them to. The hint is in the nane 'contractors'.  In my experience the easiest way to improve 'owner' project controls, is to throw out the 30 year-old clauses in contracts they issue that describe the contractor's planning obligation, and rewrite them.