There generally isn't an issue with whether you press F9 in the middle of update or after actualizing all the activities.
Personally i press F9 after updating each task to see how the progress of said task impacts the schedule in its entirety. In this way I am able to easily spot out of sequence updates which may be erroneous or a result of a change in strategy / methodology. As long as all the tasks are updated as per the current status date or data date at the end of the day, there shouldn't be an issue.
The only concern here would be if you have resources loaded and the activity type involves the following types:
Fixed Duration & Units / Time
Fixed Units / Time
In such a circumstance, you would need to be wary of how your change of data date would impact the units allocated as a change in duration would result in a change in units.
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Tue, 2022-10-18 14:45
Typically that is what I do. One reason is if your are fairly on schedule the activities that you are applying actual dates to should be close to the forecasted dates that are there. If you change the data date by 1 month they will be off by at least 1 month. Its easier to pick an actual start and or finish date in the given month than to have to scroll backwards to the previous month EVERY time you want to recored an actual start or finish date.
NO Actual dates can be after the data date and if you move the data date the early start and or finish dates will be forecasted in the next month so for ANY actuals you will have to scroll back a month.
As David said until ALL activities have been properly progressed the schedule is incorrect. Since this is a CMP schedule WITH LOGIC by not progressing one activity could impact another activity and give you a false dates.
You can schedule any time you want, any number of times. You can change the data date forwards and backwards. Until every activity is progressed to a single data date, and then the project is scheduled with that data date, the schedule is wrong.
You can schedule any time you want, any number of times. You can change the data date forwards and backwards. Until every activity is progressed to a single data date, and then the project is scheduled with that data date, the schedule is wrong.
Member for
13 yearsThere generally isn't an
There generally isn't an issue with whether you press F9 in the middle of update or after actualizing all the activities.
Personally i press F9 after updating each task to see how the progress of said task impacts the schedule in its entirety. In this way I am able to easily spot out of sequence updates which may be erroneous or a result of a change in strategy / methodology. As long as all the tasks are updated as per the current status date or data date at the end of the day, there shouldn't be an issue.
The only concern here would be if you have resources loaded and the activity type involves the following types:
In such a circumstance, you would need to be wary of how your change of data date would impact the units allocated as a change in duration would result in a change in units.
Member for
16 years 3 monthsTypically that is what I do.
Typically that is what I do. One reason is if your are fairly on schedule the activities that you are applying actual dates to should be close to the forecasted dates that are there. If you change the data date by 1 month they will be off by at least 1 month. Its easier to pick an actual start and or finish date in the given month than to have to scroll backwards to the previous month EVERY time you want to recored an actual start or finish date.
NO Actual dates can be after the data date and if you move the data date the early start and or finish dates will be forecasted in the next month so for ANY actuals you will have to scroll back a month.
As David said until ALL activities have been properly progressed the schedule is incorrect. Since this is a CMP schedule WITH LOGIC by not progressing one activity could impact another activity and give you a false dates.
Member for
9 years 9 monthsYou can schedule any time you
You can schedule any time you want, any number of times. You can change the data date forwards and backwards. Until every activity is progressed to a single data date, and then the project is scheduled with that data date, the schedule is wrong.
Member for
9 years 9 monthsYou can schedule any time you
You can schedule any time you want, any number of times. You can change the data date forwards and backwards. Until every activity is progressed to a single data date, and then the project is scheduled with that data date, the schedule is wrong.