Oracle Primavera - PM6 Member for 12 years 6 months Member for 12 years 6 months Submitted by blonjuan44 on Fri, 2022-09-02 12:10 Permalink Wow, fastest answer ever on Wow, fastest answer ever on this site. Thank you very much. Member for 12 years 6 months Member for 12 years 6 months Submitted by blonjuan44 on Fri, 2022-09-02 11:58 Permalink Wow, fastest answer ever on Wow, fastest answer ever on this site. Thank you very much. Member for 9 years 9 months Member for 9 years 9 months Submitted by David Kelly on Fri, 2022-09-02 10:56 Permalink Yes there is a trick. Some of Yes there is a trick. Some of this might not be necessary now, but I always: Group and sort by WBS Do not 'hide if empty' Always select using the left mouse button, before right-clicking and paste Log in or register to post comments
Member for 12 years 6 months Member for 12 years 6 months Submitted by blonjuan44 on Fri, 2022-09-02 12:10 Permalink Wow, fastest answer ever on Wow, fastest answer ever on this site. Thank you very much.
Member for 12 years 6 months Member for 12 years 6 months Submitted by blonjuan44 on Fri, 2022-09-02 11:58 Permalink Wow, fastest answer ever on Wow, fastest answer ever on this site. Thank you very much.
Member for 9 years 9 months Member for 9 years 9 months Submitted by David Kelly on Fri, 2022-09-02 10:56 Permalink Yes there is a trick. Some of Yes there is a trick. Some of this might not be necessary now, but I always: Group and sort by WBS Do not 'hide if empty' Always select using the left mouse button, before right-clicking and paste
Member for
12 years 6 monthsWow, fastest answer ever on
Wow, fastest answer ever on this site. Thank you very much.
Member for
12 years 6 monthsWow, fastest answer ever on
Wow, fastest answer ever on this site. Thank you very much.
Member for
9 years 9 monthsYes there is a trick. Some of
Yes there is a trick. Some of this might not be necessary now, but I always:
Group and sort by WBS
Do not 'hide if empty'
Always select using the left mouse button, before right-clicking and paste