Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Wed, 2022-07-13 16:15 Permalink you have 2 optionsoption you have 2 options option #1 copy the project then delete the codes then export it and give it to the client option #2 during the import process on the Update Project Options have the client select modify in the data type: global under the Assignment Code click in the action column and change the action to do not import also under the Assignment Code Values click in the action column and change the action to do not import in the data type: Project under the Activity Code Values click in the action column and change the action to do not import also under the Activity Codes click in the action column and change the action to do not import Log in or register to post comments
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Wed, 2022-07-13 16:15 Permalink you have 2 optionsoption you have 2 options option #1 copy the project then delete the codes then export it and give it to the client option #2 during the import process on the Update Project Options have the client select modify in the data type: global under the Assignment Code click in the action column and change the action to do not import also under the Assignment Code Values click in the action column and change the action to do not import in the data type: Project under the Activity Code Values click in the action column and change the action to do not import also under the Activity Codes click in the action column and change the action to do not import
Member for
16 years 3 monthsyou have 2 optionsoption
you have 2 options
option #1
copy the project then delete the codes then export it and give it to the client
option #2
during the import process on the Update Project Options have the client select modify
in the data type: global under the Assignment Code click in the action column and change the action to do not import
also under the Assignment Code Values click in the action column and change the action to do not import
in the data type: Project under the Activity Code Values click in the action column and change the action to do not import
also under the Activity Codes click in the action column and change the action to do not import