Thanks, you are the best. Just making sure there was not something I didn't realize. Oracle needs to use a standard because there are now so many versions everyone has to adjust it most the time, and most folks don't know you can do it yourself.
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Tue, 2022-06-28 14:51
I have not seen anything that has been lost. The only way anything can really be lost is if there is an entirely new field created by oracel in P6 version 19.3 that is not in version 16.1
Also what do you think happens when you are in verions 19.3 and select export xer file you have the option to export all the backwackwards to version 5.0
Activity id the same
duration the same
remaining duration the same
constraints the same
calendars the same
different types of predcessors and succuessors the same
Member for
12 years 6 monthsThanks, you are the best.
Thanks, you are the best. Just making sure there was not something I didn't realize. Oracle needs to use a standard because there are now so many versions everyone has to adjust it most the time, and most folks don't know you can do it yourself.
Member for
16 years 3 monthsI have not seen anything that
I have not seen anything that has been lost. The only way anything can really be lost is if there is an entirely new field created by oracel in P6 version 19.3 that is not in version 16.1
Also what do you think happens when you are in verions 19.3 and select export xer file you have the option to export all the backwackwards to version 5.0
Activity id the same
duration the same
remaining duration the same
constraints the same
calendars the same
different types of predcessors and succuessors the same
lags the same
activity codes the same
expenses the same
resources the same
forward and backward pass the same
activity types the same