Oracle Primavera - PM6 Member for 7 years 7 months Member for 7 years 7 months Submitted by CCP Magic on Sat, 2022-05-28 13:06 Permalink I would like to draw the I would like to draw the activity usage profile for any group of activities and for any project without the help of the P6. The parser has no relation with what we speak about. Member for 7 years 7 months Member for 7 years 7 months Submitted by CCP Magic on Sat, 2022-05-28 13:04 Permalink I would like to draw the I would like to draw the activity usage profile for any group of activities and for any project without the help of the P6. The parser has no relation with what we speak about. Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Fri, 2022-05-27 14:30 Permalink why do you really need these why do you really need these ? you can also use the parser in excel Member for 7 years 7 months Member for 7 years 7 months Submitted by CCP Magic on Fri, 2022-05-27 13:06 Permalink Thank you Rodel,Your reply is Thank you Rodel, Your reply is greatly appreciated. Member for 19 years Member for 19 years Submitted by Rodel Marasigan on Fri, 2022-05-27 13:02 Permalink You have two options:1) You have two options: 1) Create a layout in P6 using activity spread or resource spread then use copy and paste function to excel 2) Run these timespread tables in P6 Report with output to .csv then open in excel. Alternative options is for programmer and software developer: Create a program that automate these timespread in excel using the open database table of P6. Member for 7 years 7 months Member for 7 years 7 months Submitted by CCP Magic on Thu, 2022-05-26 17:42 Permalink Hi ZoltanThank you for your Hi Zoltan Thank you for your reply. These are the all features of Ranga: 1. import xer in excel 2. color your wbs 3. group by wbs 4. gantt chart by shape 5. gantt chart by cell format 6. create wbs dictionary 7. create resource dictionary 8. create activity code dictionary 9. extract calendar Where the spread tables can be found? Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Thu, 2022-05-26 14:42 Permalink Try Try RANGA https://prevara.tech/ Log in or register to post comments
Member for 7 years 7 months Member for 7 years 7 months Submitted by CCP Magic on Sat, 2022-05-28 13:06 Permalink I would like to draw the I would like to draw the activity usage profile for any group of activities and for any project without the help of the P6. The parser has no relation with what we speak about.
Member for 7 years 7 months Member for 7 years 7 months Submitted by CCP Magic on Sat, 2022-05-28 13:04 Permalink I would like to draw the I would like to draw the activity usage profile for any group of activities and for any project without the help of the P6. The parser has no relation with what we speak about.
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Fri, 2022-05-27 14:30 Permalink why do you really need these why do you really need these ? you can also use the parser in excel
Member for 7 years 7 months Member for 7 years 7 months Submitted by CCP Magic on Fri, 2022-05-27 13:06 Permalink Thank you Rodel,Your reply is Thank you Rodel, Your reply is greatly appreciated.
Member for 19 years Member for 19 years Submitted by Rodel Marasigan on Fri, 2022-05-27 13:02 Permalink You have two options:1) You have two options: 1) Create a layout in P6 using activity spread or resource spread then use copy and paste function to excel 2) Run these timespread tables in P6 Report with output to .csv then open in excel. Alternative options is for programmer and software developer: Create a program that automate these timespread in excel using the open database table of P6.
Member for 7 years 7 months Member for 7 years 7 months Submitted by CCP Magic on Thu, 2022-05-26 17:42 Permalink Hi ZoltanThank you for your Hi Zoltan Thank you for your reply. These are the all features of Ranga: 1. import xer in excel 2. color your wbs 3. group by wbs 4. gantt chart by shape 5. gantt chart by cell format 6. create wbs dictionary 7. create resource dictionary 8. create activity code dictionary 9. extract calendar Where the spread tables can be found?
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Thu, 2022-05-26 14:42 Permalink Try Try RANGA https://prevara.tech/
Member for
7 years 7 monthsI would like to draw the
I would like to draw the activity usage profile for any group of activities and for any project without the help of the P6.
The parser has no relation with what we speak about.
Member for
7 years 7 monthsI would like to draw the
I would like to draw the activity usage profile for any group of activities and for any project without the help of the P6.
The parser has no relation with what we speak about.
Member for
16 years 3 monthswhy do you really need these
why do you really need these ?
you can also use the parser in excel
Member for
7 years 7 monthsThank you Rodel,Your reply is
Thank you Rodel,
Your reply is greatly appreciated.
Member for
19 yearsYou have two options:1)
You have two options:
1) Create a layout in P6 using activity spread or resource spread then use copy and paste function to excel
2) Run these timespread tables in P6 Report with output to .csv then open in excel.
Alternative options is for programmer and software developer:
Create a program that automate these timespread in excel using the open database table of P6.
Member for
7 years 7 monthsHi ZoltanThank you for your
Hi Zoltan
Thank you for your reply.
These are the all features of Ranga:
1. import xer in excel
2. color your wbs
3. group by wbs
4. gantt chart by shape
5. gantt chart by cell format
6. create wbs dictionary
7. create resource dictionary
8. create activity code dictionary
9. extract calendar
Where the spread tables can be found?
Member for
16 years 3 monthsTry
Try RANGA
https://prevara.tech/