Oracle Primavera - PM6 Member for 7 years 10 months Member for 7 years 10 months Submitted by ShaohuaChen on Thu, 2019-01-24 04:53 Permalink Could you check the resource Could you check the resource usage ---graph--calcualte average ? Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Wed, 2019-01-23 13:47 Permalink what is your units per day what is your units per day set on your resource ? a quick fix would be to run a global change where budgeted cost is not equal to 0 then budgeted cost = budgeted cost / 100 or where budgeted units is not equal to 0 then budgeted units = budgeted units / 100 Log in or register to post comments
Member for 7 years 10 months Member for 7 years 10 months Submitted by ShaohuaChen on Thu, 2019-01-24 04:53 Permalink Could you check the resource Could you check the resource usage ---graph--calcualte average ?
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Wed, 2019-01-23 13:47 Permalink what is your units per day what is your units per day set on your resource ? a quick fix would be to run a global change where budgeted cost is not equal to 0 then budgeted cost = budgeted cost / 100 or where budgeted units is not equal to 0 then budgeted units = budgeted units / 100
Member for
7 years 10 monthsCould you check the resource
Could you check the resource usage ---graph--calcualte average ?
Member for
16 years 3 monthswhat is your units per day
what is your units per day set on your resource ?
a quick fix would be to run a global change
where budgeted cost is not equal to 0
then budgeted cost = budgeted cost / 100
or
where budgeted units is not equal to 0
then budgeted units = budgeted units / 100