Could you check the resource usage ---graph--calcualte average ?

Member for

16 years 3 months

what is your units per day set on your resource ?

a quick fix would be to run a global change 

where budgeted cost is not equal to 0

then budgeted cost  = budgeted cost / 100

or 

where budgeted units is not equal to 0

then budgeted units  = budgeted units / 100