Primavera 6 ver17.**

Member for

16 years 3 months

to check this setting go to the projects directory

make sure that your project is highlighted

click on the resource tab 

lower right make sure that under Resource agssignments that 

Resourcces can be assigned ot the same activity more than once is NOT checked

Member for

8 years 2 months

Agree with Zoltan - It may be that there are duplicate resources against the same activity.

Primavera does not like importing the same resource against 1 activity, as it see's the resource already in the database then updates the existing value with the new value being imported.

It is looking for the Activity ID & Resource ID during import, where it see's a match it will update.

When importing, try changing the settings on the XER Import under "Activity Resource Assignments" to "Insert New".

Do not import this as an update to the existing project, as the original resource may be duplicated where there is no duplicate in the import file.

If regularly sending XER files to others for import, on the project settings disable the setting that allows Resources to be allocated to activities more than once - I'm sure that Zoltan has already put a post out with where this setting is.

Regards,

Steven

Member for

16 years 3 months

during the import process make sure that you modify the import configuration and under Data Type:Global make sure that under resources that under the action item that insert new is checked.

Member for

16 years 11 months

Hi Zoltan,

Again It been awhile. 

No we did not do anything with the file; it is that when export using P6 17.++ some data (resources) went missing after it is opened by the receiving end also using the same version. But not all, that makes us wonder why is the new version doing that.

Our old version is 8.4 and do not havr any issues on it...

 

Ruel

 

Member for

16 years 3 months

check your resources and make sure that calculate cost from unist is NOT checked if it is run a global change to change it to no.