Individual day calendars causing negative float in P6 V8.2

Member for

16 years 3 months

Turn on your TIMES

Make sure that your TIMES are correct in you calendar meaning the start and end times of each day of the week.

Make sure that your TIMES are correct for ALL constraint dates Start milestones should be 8:00 am or the ealiest time on that calendar. Finish milestones should use 5:00 pm or the latest finish time in your calendar

Make sure that your data date TIME is correct it should be 8:00 am or the earliest start time in your calendar is 

Make sure that your project must finish by TIME is correct it should be 5:00 pm the latest finish time in your calendar.

Make sure that any activities that have an actual start started on 8:00 am or the ealiest time on that calendar.

Make sure that any activities that have an actual finsh date finished on 5:00 pm the latest finish time in your calendar.

Make sure that the milestones that have described above are assigned to the calendar

Make your durations 2 decimal and make sure that all original durations and remaining durations are in whole numbers.