Task dependent activity - right or wrong?

Member for

19 years 10 months

Hi Anthony

I agree with your approach that task calendars and resource calendars should be the same.

If there are special circumstances that require a different calendar then aplly it to both task and resource.

In Asta PowerProject there is a tick box on the resource menu which says - Use Task Calendar.

Best regards

Mike Testro