Planning, Scheduling & Programming Discussion Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Thu, 2015-06-11 10:39 Permalink Hi AnthonyI agree with your Hi Anthony I agree with your approach that task calendars and resource calendars should be the same. If there are special circumstances that require a different calendar then aplly it to both task and resource. In Asta PowerProject there is a tick box on the resource menu which says - Use Task Calendar. Best regards Mike Testro Log in or register to post comments
Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Thu, 2015-06-11 10:39 Permalink Hi AnthonyI agree with your Hi Anthony I agree with your approach that task calendars and resource calendars should be the same. If there are special circumstances that require a different calendar then aplly it to both task and resource. In Asta PowerProject there is a tick box on the resource menu which says - Use Task Calendar. Best regards Mike Testro
Member for
19 years 10 monthsHi AnthonyI agree with your
Hi Anthony
I agree with your approach that task calendars and resource calendars should be the same.
If there are special circumstances that require a different calendar then aplly it to both task and resource.
In Asta PowerProject there is a tick box on the resource menu which says - Use Task Calendar.
Best regards
Mike Testro