start date is not critical

Member for

15 years 11 months

Please check the following :-

1. The Project finish date is matching with the schedule finish date

2. If still the start date is showing float it means that somewhere the relation is open or a constrain in the project is driving the CRITICAL activities.

3. You can send the file to me to check for issues.

 

Member for

24 years 9 months

Possible options (assuming there is a difference between the milestone and the first activities float)

  1. The project start date is defined as a constraint on the first activity not the milestone and the milestone is scheduling from the project calendar start
  2. Different calendars allocated
  3. The first activity is scheduled ‘As late as possible’

Member for

21 years 10 months

Dear Gary,

Sorry that is what I mean, the first task is successor to the milestone date.

Best,

Moutaz

Member for

16 years 7 months

the first task should be the sucessor of the start milestone, not predecessor

Member for

21 years 10 months

Yes, Gary it is a milestone and the first task is the predecessor of this milestone.

Regards,

Moutaz

Member for

16 years 7 months

when you say start date is not critical, do you mean start milestone?

 

If so, check the first task that is on your critical path has a predeccesor of the start milestone