concrete tracking reports

Member for

19 years 10 months

Hi Haytham

Set up a spreadsheet with the dimensions of each concrete component - floors - columns - beams - stairs ect.

This will give you the total m3 of concrete in the project.

Put a date column in the spreadsheet.

Every day collect a copy of the concrete cube test sheets and type the date of the test against the concrete item.

You can then keep a running total of actual concrete production to compare with your planned production rate.

Best regards

Mike Testro