Planning, Scheduling & Programming Discussion Member for 20 years 5 months Member for 20 years 5 months Submitted by Jose Frade on Tue, 2014-03-25 15:40 Permalink You can use several methods. You can use several methods. in V6 you can use Global Change / Excel 1. create a user field 2. Export to Excel and populate the user field with the Act.ID you want and import back 3. Create a global change to repalce Act ID with value from User field BR JMFrade Log in or register to post comments
Member for 20 years 5 months Member for 20 years 5 months Submitted by Jose Frade on Tue, 2014-03-25 15:40 Permalink You can use several methods. You can use several methods. in V6 you can use Global Change / Excel 1. create a user field 2. Export to Excel and populate the user field with the Act.ID you want and import back 3. Create a global change to repalce Act ID with value from User field BR JMFrade
Member for
20 years 5 monthsYou can use several methods.
You can use several methods. in V6 you can use Global Change / Excel
1. create a user field
2. Export to Excel and populate the user field with the Act.ID you want and import back
3. Create a global change to repalce Act ID with value from User field
BR
JMFrade