...but if the date was showing 16th feb with the fniish on or before constraint, this is becuase your schedule is telling you it is impossible to finish by 12th dec.

Making it a mandatory constraint will make the end date change, but it doesn't mean you will achieve that end date.

 

Really, you're just hiding the problem, rather than adressing it.

This is why I do not like mandatory constraints.

Member for

15 years

Hi Limson,

Thanks for your reply

Regards

Sunil

Member for

24 years 1 month

Hi Sunil,

If you dont want your end date to move, used "Mandatory Finish"

Cheers,

Daniel