Thanks again Raymund, a friend here also suggested the same solution. However, I think I finally got around to group by Activity code as well as WBS. I appreciate your inputs man!
Cheers,
Abdulhafiz
Member for
15 years 11 months
Member for15 years11 months
Submitted by Raymund de Laza on Tue, 2012-03-20 09:04
Thanks Raymund, I follow your reasoning but the challenge Im having with Activity codes is that is will just group the schedule into "Milestones" and "No Milestones" categories which is not so cool for presentation purposes. Or is there a way to group by Activity codes as well as WBS especially in P6? Thanks again for inputs.
Regards,
Abdulhafiz
Member for
15 years 11 months
Member for15 years11 months
Submitted by Raymund de Laza on Tue, 2012-03-20 07:11
I suggest you insert those key dates within the same WBS with the related tasks and create acitivty codes to group milestone/key dates altogether for reporting purposes organized by activty codes accordingly.
Member for
14 years 3 monthsThanks again Raymund, a
Thanks again Raymund, a friend here also suggested the same solution. However, I think I finally got around to group by Activity code as well as WBS. I appreciate your inputs man!
Cheers,
Abdulhafiz
Member for
15 years 11 monthsCreate another Activity codes
Create another Activity codes with the same name as your WBS.
Member for
14 years 3 monthsThanks Raymund, I follow your
Thanks Raymund, I follow your reasoning but the challenge Im having with Activity codes is that is will just group the schedule into "Milestones" and "No Milestones" categories which is not so cool for presentation purposes. Or is there a way to group by Activity codes as well as WBS especially in P6? Thanks again for inputs.
Regards,
Abdulhafiz
Member for
15 years 11 monthsAbdulHafiz, I suggest you
AbdulHafiz,
I suggest you insert those key dates within the same WBS with the related tasks and create acitivty codes to group milestone/key dates altogether for reporting purposes organized by activty codes accordingly.