AS BUILT PROGRAM

Member for

16 years 5 months

Hi friends,

the first I submit is the updated approved baseline, they reject it and request for an as built program. The project starts last 9 August 2011 and contract completion date is 26 December 2011. After several submissions we come up with Remaining Works for February 2012 considering 20% of the project is completed. Its really a new program which I incorporate the  program of the subcontractors as well (my manager thinks of getting subcon to make it more fast). I check our available resources and talk to alll engineers for their scope. The client and consultant is checking only hard copy  in pdf file.

 

 

 

Member for

16 years 5 months

Hi friends,

the first I submit is the updated approved baseline, they reject it and request for an as built program. The project starts last 9 August 2011 and contract completion date is 26 December 2011. After several submissions we come up with Remaining Works for February 2012 considering 20% of the project is completed. Its really a new program which I incorporate the  program of the subcontractors as well (my manager thinks of getting subcon to make it more fast). I check our available resources and talk to alll engineers for their scope. The client and consultant is checking only hard copy  in pdf file.

 

 

 

Member for

19 years 10 months

Hi Mervyline

Raymond is pointing in the right direction.

If you have not started the work yet but there are delays in starting then you should be reporting a delay to the completion date.

This request for an "as built" programme is a red herring to distract you from the real issue.

Issue an updated programme at thr report date showing 0% progress on each task and reschedule - then ask for an extension of time.

Best regards

Mike Testro

Member for

15 years 11 months

Hi,

The approved program is considered as the Baseline Program. Due to the delays incurred, the Client instructed you to prepare an Updated (As-Built) schedule based from the approved program reflecting the actual situation in the Project, which will now then showing a delay in the completion date. The client might be interested to know the impact as a result of the delays.

Is this delays in approval beyond your control?