Oil/Gas/LNG Construction - Production Rate

Member for

17 years 5 months

Ronald,

Productivity will differ based on projects and the priority of particular activities.

I suggest as follows.

1. Take the dia inches to be welded for each category.

2. Check the welders available for category.

3. On a weekly basis, check the no of dia inches welded.

I hope in this way you can calculate the productivity.

Member for

13 years 8 months

Good day to all of u,

Can someone help email me oil&gas pipeline construction schedule, im new to this kind of work,im willing to learn this, it will really be a big help for me on how it goes.

thanks in advance. Nicole

Member for

22 years 3 months

Thanks Sreejith,



We are try to look for actual values (based on experiences) but if there are detailed database I think it will help and or we just come up with some sort of approximation.



Ronald

Member for

17 years 7 months

Hi Ronald,

This is a very good effort.

But measuring activity specific man hours is really tough.

Especially when it is a fast track project.

In our organisation we are doing such efforts for developing norms. This is done by analysing historical data and arriving at ’Parameters’ and values.

Are you looking for a detailed database specifying type of weld, schedule..etc etc or broad approximations?



Cheers



Sreejith