Right now I am working in a Microtunneling project.In the Tender stage with limited information we submited one Tender program with a sequence and duration,we got the work also.
Once the work awarded Client changed the sequence and duartion with current situation with the joint meeting of We Maincontactor and the tunneling contractor.
Nw My Q.S is saying that we have to submit a Base program with Tender sequence and Duration which is not going to happend.
What I have to do ???/Please help
Member for
15 years 11 months
Member for15 years11 months
Submitted by Raymund de Laza on Sat, 2012-03-03 12:26
Tender Program = Preliminary Master Schedule attached with the Tender Docs. This part of the Tender Doc will present how you will plan to execute the Tender Project. Baseline Program = Initial Schedule accepted or approved by client in the beginning of the implementation of Project. This detailed schedule will present how to execute the project on hand.
Member for
16 years 1 monthThank you sirRight now I am
Thank you sir
Right now I am working in a Microtunneling project.In the Tender stage with limited information we submited one Tender program with a sequence and duration,we got the work also.
Once the work awarded Client changed the sequence and duartion with current situation with the joint meeting of We Maincontactor and the tunneling contractor.
Nw My Q.S is saying that we have to submit a Base program with Tender sequence and Duration which is not going to happend.
What I have to do ???/Please help
Member for
15 years 11 monthsArun, There is no specific
Arun,
There is no specific rules for such.
Member for
16 years 1 monthThank you Raymond Is there
Thank you Raymond
Is there any Mandatory rule that we have to follow the same duration and sequence
of Tender program in the Base line program????
Regards
Arun Vasanth
Member for
15 years 11 monthsArun, Tender Program =
Arun,
Tender Program = Preliminary Master Schedule attached with the Tender Docs. This part of the Tender Doc will present how you will plan to execute the Tender Project.
Baseline Program = Initial Schedule accepted or approved by client in the beginning of the implementation of Project. This detailed schedule will present how to execute the project on hand.