Performance % Complete

Member for

13 years 9 months

Thanks for your guidance.

 

Regards,

BIM

Member for

13 years 9 months

Performance complete is a function of actual cost in relation to cost at completion in a cost loaded programme, generally used for EV analysis.  It can be on activity level or at summary level.The performance complete value is usually the activity %complete value. (Not the unit%, duration% or physical %).Also, the values in the performance complete are stored whenever you execute the store project performance function.

Member for

14 years 1 month

Preformance % comp. work only if your schedule is cost loaded ...

Member for

21 years 1 month

Hi

 

Performance % complete is a 'roll up' of all EV earned through Physical % complete

Ie if you have a number of tasks that collectively add up to a EV £100 and the total budget is £1000 the Performance % complete is 10%

 

Hope this helps

 

Regards

 

James