Performance complete is a function of actual cost in relation to cost at completion in a cost loaded programme, generally used for EV analysis. It can be on activity level or at summary level.The performance complete value is usually the activity %complete value. (Not the unit%, duration% or physical %).Also, the values in the performance complete are stored whenever you execute the store project performance function.
Member for
14 years 1 month
Member for14 years1 month
Submitted by ravigehlotudr1 on Mon, 2012-02-06 16:39
Member for
13 years 9 monthsThanks for your
Thanks for your guidance.
Regards,
BIM
Member for
13 years 9 monthsPerformance complete is a
Performance complete is a function of actual cost in relation to cost at completion in a cost loaded programme, generally used for EV analysis. It can be on activity level or at summary level.The performance complete value is usually the activity %complete value. (Not the unit%, duration% or physical %).Also, the values in the performance complete are stored whenever you execute the store project performance function.
Member for
14 years 1 monthPreformance % comp. work only
Preformance % comp. work only if your schedule is cost loaded ...
Member for
21 years 1 monthHi Performance % complete
Hi
Performance % complete is a 'roll up' of all EV earned through Physical % complete
Ie if you have a number of tasks that collectively add up to a EV £100 and the total budget is £1000 the Performance % complete is 10%
Hope this helps