Even when you assign a baseline and export it to .XER file, when you import and then open , you could see that baseline column shows the dates of early start and early finish and not the actual baseline dates, which implies that the baseline is not getting exported into the .XER file.
So when you make a schedule update and preserve it in .XER file, the baseline doesn't follow that file.So you have to save the original baseline and re assign it to the schedule update each time you update the schedule.
You always have baseline dates, even when no baseline is assigned. When no baseline is assigned, your current Planned Dates are displayed as the baseline dates. This is probably why you think that they have ‘changed.’ The baseline dates did not change, the baseline probably did not transfer or it is no longer assigned. Good luck!
Member for
13 years 11 monthsRonald,Even when you assign a
Ronald,
Even when you assign a baseline and export it to .XER file, when you import and then open , you could see that baseline column shows the dates of early start and early finish and not the actual baseline dates, which implies that the baseline is not getting exported into the .XER file.
So when you make a schedule update and preserve it in .XER file, the baseline doesn't follow that file.So you have to save the original baseline and re assign it to the schedule update each time you update the schedule.
Please let me know if there is a better option
Best Regards,
San
Member for
13 years 11 monthsYou are right SM, baseline
You are right SM, baseline doesn't get exported.
Thanks
BR,
San
Member for
22 years 10 monthsSan, You always have baseline
San,
You always have baseline dates, even when no baseline is assigned. When no baseline is assigned, your current Planned Dates are displayed as the baseline dates. This is probably why you think that they have ‘changed.’ The baseline dates did not change, the baseline probably did not transfer or it is no longer assigned. Good luck!
Member for
13 years 11 monthssan TSWhen you export .XER
san TS
When you export .XER file then Baseline is not exported.You hace to Restore it.
Regards