Hi AB Timo 

 

If you want to define new resource ,first thing is to create a resource (For Eg.- abc ) in resource dictionary then move to the respective activity , choose resource tab option  from activity details ,click add resource option and select the filter ""All Resource"" where you can find the newly created resource (abc) then assign to it

 

Cheer's 

Shahul

Member for

16 years 11 months

Hi AB Timo

When you open resource pool window layout in that, resource icon marked with arrow mark symbol shows currently active resource available for the opened project

 

Regards

Shahul

Member for

14 years 4 months

Hi Shahul

Thanks for you Help.But still i can't find the solution.In P6 there are three options

1- Filter by "All Active Resources"

2- Filter By "All Resources"

3-Filter By "Current Project Resources"

 

The Issue I am facing is that i want not to see other Resources in My New Project.I want to define new resources but when I Select "Current Project Resource" and then Press "Add" Button the Filter Automatically Changes to "all REsources"...I have also Tried for "All Active Resources But its not working Either..Can you please explain what yoi have just said.I think i am Not getting it

 