Driving Predecessor Activity

Member for

16 years 7 months

Rhys:

 

Correct.

A driving relationship is one which defines the earliest start or finish date (depending on wether it is FS, FF etc) of the sucessor to that relationship.

 

Obviously as the schedule is progressed and changes to durations and logic happen, the relationship which drives a particular actvity can also change.

Member for

14 years 2 months

Hello

A quick question in relation to the Driving Predecessor or Successor.

 

I have some activities that are ticked as critical and driving, so does that mean that activity is driving the selected activity.

i.e.  The predecessor is before so when that has finished this activity will start if its a FS relationship?

The Successor is after so if its a Driving activity does that start at the same time the linked activity starts as its a SS relationship.

 

Thanks

Member for

14 years 4 months

Thanks Gary You Really Made it Simple for me.

Member for

16 years 7 months

1) Select View > Show on Bottom > Activity Details

2) Left click on an activity

3) From the activity details section at the bottom of the screen, select either the "predecessors" or the "relationships" tab (If neither tab is there, right click > Customise Activity details > add them)

4) You should now see all the predecessors of the activity on which you clicked. Right click on one of the predecessor columns > Customise Predecessor Columns > add the "Driving" column from the "General" group

5) any predecessor which has a "Yes" in the "Driving" column, is driving that activity.

Member for

14 years 4 months

Hi Mike,

Can you Please Elaborate a little More about the  "Vertical Link"

 

Best Regards

Member for

14 years 4 months

hi gary

I am Using Primaver P6

Regards

Member for

19 years 10 months

Hi Fiaz

The vertical link will most likely be the driver.

Best regards