You will get a lot of contradictory advice but the best advice I can give you is use only FS links and only use lags to represent drying out or curing periods - set to Calendar Days

Any other form of lags is bad planning practice.

See the debate that I started on Ban These Planning Abominations.

Best regards

Mike Testro