Without drawings and specifications you cannot make a good estimate, it is not the same for different block size, not the same production rate for blocks to be installed on the ground than for blocks to be installed using scaffolding. Also the vertical and horizontal reinforcement matter. That is why most companies do not outsource scheduling unless the specifications call for a scheduling software they do not know. It is a pity industry have not realized that scheduling should be done in-house, by the team that will be in charge of the means and methods. We have some specifications that even require the contractor to hire an external scheduler to use their particular software choice, unbelievable but true.
Member for
16 years 1 month
Member for16 years1 month
Submitted by Arun Vasanth on Fri, 2011-09-02 09:42
Production rate in Planning Planet is great, but I think it will be more meaningful if the Production Rate will be associated with basic Crew Description and Equipment Detail.
m2/mr means some production rate per hour for a crew that can be a mason plus a helper
m2/m-hr would be production rate per man-hour
Production rates without crew description are misleading, even per man-hour, you might have several production rates depending on the crew composition. It is not the same moving dirt with a 10-cm truck than with a 20-cm truck for one hour or one man-hour. It is not the same placing concrete with a wheelbarrow than with a 90-cm per hour concrete pump that can swallow several concrete trucks in an hour with ease, two chutes side by side so there is no waiting between trucks.
Member for
16 years 7 monthsDear All: If anyone wants the
Dear All:
If anyone wants the productivity info from Arun, please send him a private message with your email ID (click on the little envelope next to his name).
I'm locking this thread before it becomes full of begging letters.
Member for
14 years 11 monthsDear Mr.Arun,Please send me
Dear Mr.Arun,
Please send me a copy as well my email is d.cell@yahoo.com
Thanks in advance
Dura
Member for
14 years 11 monthsDear Mr.Arun,Please send me
Dear Mr.Arun,
Please send me a copy as well my email is d.cell@yahoo.com
Thanks in advance
Dura
Member for
18 years 3 monthsHI Arun Can u plz send me a
HI Arun
Can u plz send me a copy to yakub_sky@yahoo.co.in or yakub.sky@gmail.com
Thanks in advance,
Regards,
Shaik
Member for
18 years 3 monthsHi can u plz send me a copy
Hi can u plz send me a copy on yakub_sky@yahoo.co.in or yakub.sky@gmail.com
thanks in advance
Regards,
Shaik
Member for
16 years 2 monthsHello Mr.Arun,Can i have a
Hello Mr.Arun,
Can i have a copy as well my mail is sjustinjames@gmail.com
Thanks & Regards
Justin
Member for
15 years 1 monthDear Mr. Arun, Please send me
Dear Mr. Arun,
Please send me the productivity rates at use private message service
Regards,
Owais
Member for
21 years 8 monthshttp://www.escsi.org/uploaded
http://www.escsi.org/uploadedFiles/Technical_Docs/SmartWall_Masonry/370…
Without drawings and specifications you cannot make a good estimate, it is not the same for different block size, not the same production rate for blocks to be installed on the ground than for blocks to be installed using scaffolding. Also the vertical and horizontal reinforcement matter. That is why most companies do not outsource scheduling unless the specifications call for a scheduling software they do not know. It is a pity industry have not realized that scheduling should be done in-house, by the team that will be in charge of the means and methods. We have some specifications that even require the contractor to hire an external scheduler to use their particular software choice, unbelievable but true.
Member for
16 years 1 monthDear Friends I got the
Dear Friends
I got the Productivity rate from a Engineer who is silent the Forum (Mr.Pinan).
Iam very thankful to Mr.Pinan.
If any body wants the productivity with Crew Please post their email ID...
This productivity we can use for GCC Only....
Regards
Arun
Member for
16 years 1 monthDear FriendsIam Supporting
Dear Friends
Iam Supporting Nidan...
We planners have to prepare a production rate based on the manpower using..
for eg 1000 m2 block work
10 Block builders its propotion of helpers..
If any body have please share...
Arun
Member for
14 years 10 monthsHi Planners, Production rate
Hi Planners,
Production rate in Planning Planet is great, but I think it will be more meaningful if the Production Rate will be associated with basic Crew Description and Equipment Detail.
Thanks,
Nanding
Member for
19 years 10 monthsHi Arun The most precise way
Hi Arun
The most precise way to get production rates for your project is to look at the tender breakdown.
The individual rates should be set at Labour - Plant - Material.
The money can be converted to hours using the labour rate per hour.
If there is no individual labour rate then apply a reasonable labour percentage - 35% to 40% for blockwork
You should also take account of the other items related to blockwork productivity:
Openings and lintels
Angle head restraints
M&E Openings
Fire Proofing etc.
These should all be added to the blockwork hours and then allocated pro rata to your programme tasks.
Best regards
Mike Testro
Member for
21 years 8 monthsm2/mr means some production
m2/mr means some production rate per hour for a crew that can be a mason plus a helper
m2/m-hr would be production rate per man-hour
Production rates without crew description are misleading, even per man-hour, you might have several production rates depending on the crew composition. It is not the same moving dirt with a 10-cm truck than with a 20-cm truck for one hour or one man-hour. It is not the same placing concrete with a wheelbarrow than with a 90-cm per hour concrete pump that can swallow several concrete trucks in an hour with ease, two chutes side by side so there is no waiting between trucks.